S&J Construction installed approximately 1765-feet of 8-inch DIP water line from Station 264+00 to Station 246+35. All pipes were installed according to design specifications. S&J installed hay bales for erosion control. S&J also installed the fire hydrant at Station 264+25. At Station 255+00, S&J bored under the driveways and poured grout around the pipe. |