The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.
|
Contract III: Pump Station
|
|
Summary of Work Performed this week: 10/10/2009
|
|
Carson & Associates, Inc.: General Contractor
Carson & Associates oversaw work listed below and placed rebar for the 24-inch retaining
wall. |
|
Harvill Byrd: Subcontractor
Harvill Byrd continued minor fabrication of conduit and performed Megger testing on wires
from Primary Feed PMT to Automatic Transfer Switch. |
|
Howell Utility: Subcontractor
Howell Utility began pumping water from weekend rain and placing rebar for the 24-inch
retaining wall footer. On Tuesday, they poured 16yd3 at 9:00 a.m. Visqueen was used to
cover the slab for protection from rain. GHBW was onsite and all tests passed within
specifications. They began placing rebar and forms for 24-inch DIP Retaining Wall. Howell
Utility removed wet well covers and barricaded the area. On Wednesday, they plugged the
existing manhole to prepare for working inside the wet well. The attempt failed and a
heavier duty plug is scheduled to arrive. They began with a preliminary washing of the wet
well to prepare for a Confined Space Entrance. |
Edwards Metal Inc.: Subcontractor
Edwards Metal, Inc. performed minor cleanup and continued placing supply and return
plenums and support. |
|