EMERGENCY CONTACT: (501)223-1509


The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.

Contract III: Pump Station
Summary of Work Performed this week: 10/17/2009
Carson & Associates, Inc.: General Contractor
Workforce/Manpower: 1 Superintendent, 1 Foreman, 1 Operator, 0 Laborers
Carson & Associates oversaw work listed below.
Harvill Byrd: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 2 Laborers Harvill Byrd continued with minor fabrication of misc. conduit. They removed the existing unit heater.
Howell Utility: Subcontractor
Workforce/Manpower: 1 Superintendent, 1 Foreman, 0 Operators, 3 Laborers
Howell Utility began pumping water from 24-inch retaining wall excavated area. On Wednesday, Howell Utility completed placing forms for the 24-inch DIP retaining wall and poured 10yd3 at 12:00 noon. They later removed forms from the 24-inch retaining wall. They began constructing a canopy to cover the wet well for protection of weather to prepare for working in the wet well. Plans to plug the existing line allowing access into the wet well is scheduled for Monday, October 18, 2009.
Little Rock Fence Company: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 0 Laborers
Little Rock Fence Company completed installation of gates on west end of site as per CPR No.5. Max Harding is to supply a temporary chain and lock to secure the site for the weekend.
ARC Electric Company Inc.: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 2 Laborers
ARC Electric Company Inc. began fabrication of conduit for HVAC thermostat.
Other Notes:
Clyde Frost will be the RPR onsite on Monday, October 18, 2009 from 7:00 a.m. to 12:00 noon. His contact number is 501-766-0095. Dale Gilbert was onsite to disconnect existing grinder. Monthly Meeting was on Wednesday, October 14, 2009.