Contract III: Pump Station
Summary of Work Performed this week: 10/30/2009
Carson & Associates, Inc.: General Contractor
Workforce/Manpower: 1 Superintendent, 1 Foreman, 1 Operator, 3 Laborers
Carson & Associates performed minor cleanup work and repaired SWPPP issues as noted on the SWPPP Inspection Form dated 10/26/09. The SWPPP Construction Site Notice has been posted at the site entrance. They replaced the Construction Sign taken down during the construction by S.J. Louis and placed the SWPPP Mailbox. They received the MCC and Bar Screen and have placed the MCC in the new Electrical Room. C&A began removing the wet well grating imbeds. They continued installing ventilation systems for the wet well confined space entrance and continued pressure washing the walls. C&A pulled the existing 150 HP Pump on the south end of the wet well and have partially plugged the wet well. On Thursday and Friday, Carson & Associates performed no work.
Harvill Byrd: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 2 Laborers
Harvill Byrd continued minor demo work of the existing electrical in the Generator room and began installation and connection to the new Motor Control Center (MCC).
Rain for Rent: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 0 Laborers
Rain for Rent was onsite for inspection of the Bypass system.
Other Notes:
S.J. Louis continued access through the LMPS’s Northwest gate and delivered Pipe and Manholes. S.J. Louis is reminded of their speed throughout the site and 5 MPH Speed Limit signs have been posted. LRW Maintenance was onsite to remove hydraulics from the existing Grinder.