The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.

Contract II: Construction of Wastewater Treatment Facility
Summary of Work Performed this week: 11/06/2009
MFCC: General Contractor
Workforce/Manpower:
1 Superintendent, 4 Foremen, 5 Operators, 10 Carpenters, 3 Pipefitters, 11 Carpenter Helpers, 11 Laborers Max Foote Construction Co. worked a five day work week.
Monday, 11-02-09,
MFCC finishers continued cleaning and patching the upper Aeration Basin walls. Carpenters removed exterior forms from the U.V. channel walls. Carpenters began installing forms for the south A-pass strut beams. Carpenters continued to install wall forms for the Aeration Basin outfall box. Operators continued excavating MH-1 discharge piping at the Administration building. Carpenters continued installing shoring package for the Clarifier drive deck. Operators began removing spoils from the wall-A area and backfilling the road in front of the Headworks building.
Tuesday, 11-03-09,
MFCC finishers continued cleaning and patching the upper Aeration Basin walls. Finishers placed 4.5yds of concrete for the south A-pass strut beams. Carpenters continued installing wall forms for the Aeration Basin outfall box. Operators continued excavating MH-1 discharge piping at the Administration building. Carpenters continued installing shoring package for the Clarifier deck. Finishers placed 17yds of concrete for the northeast upper Aeration Basin jumper wall. Field test were conducted; A/E= 4.6, SL=6-inch, Temp=72 degrees
Wednesday, 11-04-09,
MFCC finishers continued cleaning and patching the upper Aeration Basin walls. Carpenters continued installing forms for the south A-pass strut beams. Carpenters completed installation of wall forms for the Aeration outfall box. Operators continued excavating MH-1 discharge piping at the Administration building. Carpenters continued installing the shoring package for the Clarifier deck. Finishers placed 40yds of concrete for the Aeration Basin outfall box. Field test were conducted; A/E=4.5, SL=2-inch,
Thursday, 11-05-09,
MFCC finishers continued cleaning and patching the upper Aeration Basin walls. Carpenters completed placement of the south A-pass strut beams. Carpenters worked installing gang forms for the upper RAS stairwell walls. Operators continued excavating MH-1 discharge piping at the Administration building. Solid rock has been encountered and excavation is slow. Carpenters continued installing the shoring package for the Clarifier drive deck. Carpenters began removing gang forms from the completed east side jumper walls.
Friday, 11-06-09,
MFCC finishers continued cleaning and patching the upper Aeration Basin walls. Carpenters began removing forms from the south D-pass strut beams. Carpenters completed installing gang forms for the upper RAS stairwell walls. Operators continued excavating MH-1 discharge piping at the Administration building. Carpenters continued installing the shoring package for the Clarifier drive deck. Carpenters continued removing gang forms from the completed east side jumper walls. Carpenters began installing forms for the east RAS jumper wall. Finishers poured the upper RAS stairwell wall. Finishers poured the effluent Aeration and RAS divider wall.
Electrique Corporation: Subcontractor
Workforce/Manpower: 1 Superintendent, 1 Foreman, 2 Helpers
E.C. worked all week installing conduits for lighting and receptacles in the Odor Control building.
Midwest Coatings: Subcontractor
Workforce/Manpower: 1 Superintendant, 1 Foreman, 1 Painter
Midwest Coatings continued priming and painting the interior CMU walls of the Headworks building.
Jocon Incorporated Building Erectors: Subcontractor
Workforce/Manpower: 1 Superintendant, 1 Foreman, 5 Ironworkers
Jocon Inc. worked erecting the structural steel for the Blower building.
DMG Masonry: Subcontractor
Workforce/Manpower: 1 Superintendant, 2 Foremen, 10 Masons
DMG continued installing the brick veneer for the west wall of the Headworks building. They continued installing the veneer for the Odor Control building chimney stack. They are 95%complete with the block installation at the Filter building.