The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.
|
Contract II: Construction of Wastewater Treatment Facility
|
Summary of Work Performed this week: 11/14/2009
|
MFCC: General Contractor
Workforce/Manpower: 1 Superintendent, 4 Foremen, 5 Operators, 10 Carpenters, 3
Pipefitters, 11 Carpenter Helpers, 11 Laborers
Max Foote Construction Co. worked a five day work week.
|
Monday, 11-09-09,
MFCC finishers continued cleaning and patching the upper Aeration
Basin walls. Carpenters completed removing forms from the south D-pass strut beams.
Carpenters completed installing gang forms for the upper RAS stairwell walls. Operators
continued excavating MH-3 discharge piping east to the Headworks building. Carpenters
continued installing shoring package for the Clarifier deck. Carpenters completed removing
gang forms from the completed east side jumper walls. Carpenters began installing forms for
the east RAS room jumper walls. Carpenters began removing the north gang forms from the
Aeration Basin outfall box.
|
Tuesday, 11-10-09,
MFCC finishers continued cleaning and patching the upper Aeration
Basin walls. Carpenters began installing the plate embeds for the Clarifier drives. Carpenters
and operators worked backfill and grading around the U.V. structure. Operators continued
excavating MH-3 discharge piping east to the Headworks building. Carpenters continued
installing shoring package for the Clarifier deck. Operators worked entrance road grading
and cleanup around the Administration area. Carpenters continued installing forms for the
east RAS room jumper walls. Carpenters continued removing the north gang forms from the
Aeration Basin outfall box.
|
Wednesday, 11-11-09,
MFCC finishers continued cleaning and patching the upper
Aeration Basin walls. Carpenters continued installing the plate imbeds for the Clarifier drives.
Carpenters and operators demobilized unused gang and structural forms. Operators
continued excavating MH-3 discharge piping east to the Headworks building. Carpenters
continued installing decking and forms for the Clarifier drive deck. Carpenters began
installing jumper gang forms for the southwest Aeration Basin wall. Carpenters continued
installing forms for the east RAS room jumper walls. Carpenters continued removing the
north gang forms from the Aeration Basin outfall box.
|
Thursday, 11-12-09,
MFCC Finishers continued cleaning and patching the upper Aeration
Basin walls. Carpenters continued installing the plate embeds for the Clarifier drives.
Carpenters and operators continued demobilizing unused gang and structural formwork.
Laborers continued backfilling the south end of the U.V. building. Carpenters continued
installing decking and forms for the Clarifier deck. Carpenters continued removing gang
forms from the Aeration Basin outfall box. Carpenters continued installing gang forms for the
east RAS room jumper walls.
|
Friday, 11-13-09,
MFCC finishers continued cleaning and patching the upper Aeration
Basin walls. Carpenters completed installing the plate embeds for the Clarifier drives.
Carpenters and laborers worked cleaning the RAS room basement area. Laborers continued
backfilling the south end of the U.V. building area. Carpenters completed installing decking
and formwork for the Clarifier deck. The rod busters are scheduled to install rebar for the
deck 11/16/09. Carpenters completed removing the north gang forms from the Aeration
Basin outfall box. Carpenters continued installing forms for the east RAS room jumper walls.
Operators and pipefitters continued installing MH-3 drain piping the Headworks.
|
 |
Electrique Corporation: Subcontractor
Workforce/Manpower: 1 Superintendent, 1 Foreman, 2 Helpers
E.C. worked all week installing conduits for lighting and receptacles in the Odor Control
building.
|
Midwest Coatings: Subcontractor
Workforce/Manpower: 1 Superintendant, 1 Foreman, 1 Painter
Midwest Coatings continued priming and painting the interior CMU walls of the Headworks
building.
|
Jocon Incorporated Building Erectors: Subcontractor
Workforce/Manpower: 1 Superintendant, 1 Foreman, 5 Ironworkers
Jocon Inc. worked erecting the structural steel for the Blower building and installing the
soffits for the Odor Control building.
|
DMG Masonry: Subcontractor
Workforce/Manpower: 1 Superintendant, 2 Foremen, 10 Masons
DMG completed installing the CMU block for the west wall of the Headworks building. They
completed installing the veneer for the Odor Control building chimney stack. They completed
the block installation at the Filter building and veneer on the west wall.
|
Henley Construction: Subcontractor
Workforce/Manpower: 1 Superintendant, 1 Foreman, 3 Masons
Henley worked installing the east end of wall-B up to course 4.
|