The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.
|
Contract IV: Conveyance (Pipeline)
|
|
Summary of Work Performed this week: 11/14/2009
|
West End Conveyance (Ranch Properties) –
The west end crew started the week at East Pinnacle Road. The ARV at Station 13+75
was completed and the major piping inside the vault was installed. Survey crews marked the
alignment for the road restoration at the end of East Pinnacle Road. The crew restored the
contours in the area and worked on SWPPP compliance before mobilizing the heavy
equipment to the LMPS to begin installation of the gravity sewer line.
On Wednesday, the crew began the installation of the gravity sewer line. The 36-inch
CCFRMP was installed within the plans and specifications. The trench excavation has shown
to be stable and dry for the most part. Dewatering with pumps was completed when it was
necessary. The sewer line was installed from Station 20+00 through Station 24+30 by the end
of the week. The manhole installation at Station 20+50 was accomplished with a minor
change. The base material will be #67 stone for the manholes, as approved by Craig Johnson.
The trench type will remain Type III as long as the conditions are favorable to the type.
GHBW have been notified and will make field observation of the trench conditions. GHBW
will advise on when the trench type should change to cement stabilized sand.
The utility crew took advantage of the great weather to continue with seeding and
mulching for stabilization along the easement. The crew mulched areas from Station 136+00
through Station 11+00. The SWPPP report for next week will reflect the stabilized areas in
detail.
Max Hardin began removal of the water crossing at Station 102+00. The excavated
materials are being stockpiled at Station 130+00 to be used for the next water crossing.
|
East End Conveyance -
Monday, November 2, 2009, the east end pipe crew removed both 36-inch RCPs at
approximately Station 253+22. S.J. Louis will replace both cuts with full 8-foot joints of 36-inch
RCP, as requested. Rick Roberts (Pulaski County) was onsite to observe construction
activities. The east end S.J. Louis crew was able to control the water infiltration into the
trench. S.J. Louis excavated to the required depth to maintain a minimum of 2-feet of
separation between the 36-inch PVC force main and the 36-inch RCP. S.J. Louis placed one
joint of pipe, but they did get under the double 36-inch RCP.
Tuesday, November 3, 2009, the east end S.J. Louis pipe crew completed the replacement
and stabilization of the double 36-inch RCP located at approximately Station 255+22. Also, S.J.
Louis crews replaced and stabilized the 18-inch CMP at approximately Station 270+00. Rick
Roberts was onsite to observe the repair at both locations. S.J. Louis will continue
approximately 200-feet to the final ARV vault installation at Station 251+00. The vault should
be in place Thursday, November 12, 2009. S.J. Louis will then precede approximately 50-feet
to make the tie-in at Station 250+50. The east end S.J. Louis crew is scheduled to demobilize
from the project site on Saturday, November 14, 2009.
Wednesday, November 4, 2009, S.J. Louis continued with pipeline installation from the
Station 253+00+/-. The S.J. Louis east end pipe crew broke the bell of the pipe. Repairs were
made and pipeline production continued for 3 full joints of pipe to approximately Station
252+40. Rick Roberts (Pulaski County) was called out by Sherman Smith to the project site to
observe construction. The pipe trench conditions at approximately Station 252+80 were
observed by the RPR (Mike Hoggard) to be good.
Thursday, November 5, 2009, east end S.J. Louis pipe crew placed approximately 190-
feet of 36-inch PVC pipe from Station 252+40 to Station 250+50. S.J. Louis will continue with
the tie-in at Station 250+50 and placement of the final ARV vault at Station 251+00 tomorrow,
November 13, 2009. The S.J. Louis east end crew will demobilize and leave the project over
the weekend.
Friday, November 6, 2009, the east end pipe crew completed the tie-in placing a sleeve at
approximately Station 250+80. The crew installed the pipe according to design specifications.
The S.J Louis east end pipe crew will demobilize over the weekend and leave the project. The
S.J Louis utility crew will complete the ARV vault installation at Station 251+00 on Saturday,
November 14, 2009.
Saturday, November 7, 2009, Jesse Alcorta and several crewmen worked on the ARV in
County Farm Road at Station 251+00. The area was excavated and reinforcing steel was
added. The concrete for the base was placed at 10:45 a.m. Aaron, GHBW, was onsite to test
the concrete and take cylinders. The tests were within the design specifications. The crew set
the ARV at Station 251+00 and completed backfilling the area. NOTE: The concrete supplier
was Levy Concrete. Levy Concrete was not the original supplier and the actual mix design
delivered for the pour was not submitted for review. SJ Louis submitted a request to Pulaski
County for Saturday work but no notice was received from Pulaski County authorizing
Saturday work in County Farm Road.
|
|
|