EMERGENCY CONTACT: (501)223-1509


The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.

Contract III: Pump Station
Summary of Work Performed this week: 11/19/2009
Carson & Associates, Inc.: General Contractor
Workforce/Manpower: 1 Superintendent, 1 Foreman, 0 Operators, 4 Laborers
Carson & Associates removed the existing pump guide rails on the existing Pumps No. 1, 2, 3 and 4. They began placing shoring to prepare for pouring the wet well beams.
Harvill Byrd: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 2 Laborers
Harvill Byrd continued rerouting electrical to the new MCC.
Rain for Rent: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 4 Laborers
Rain for Rent was onsite for maintenance of the temporary wet well sump pump.
Arkansas Coring and Drilling, Inc: Subcontractor
Workforce/Manpower: 1 Superintendent, 0 Foremen, 0 Operators, 4 Laborers
Arkansas Coring and Drilling, Inc. continued coring the 54-inch core at the Bypass and wet well.
Edwards Metal, Inc: Subcontractor 1 Superintendent, 0 Foremen, 0 Operators, 1 Laborer
Edwards Metal, Inc. continued placement of the interior HVAC ductwork at the electrical room and supports for the HVAC Plenums.
Johnson Controls: Subcontractor 1 Superintendent, 0 Foremen, 0 Operators, 1 Laborer
Johnson Controls continued placement of conduit for the thermostats.
Other Notes:
S.J. Louis accessed through the LMPS to deliver the rock, pipe, and manhole.