EMERGENCY CONTACT: (501)223-1509


The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.

Contract IV: Conveyance (Pipeline)
Summary of Work Performed this week: 11/19/2009
West End Conveyance (Ranch Properties) –
The west end pipe crew worked on the gravity sewer line in the Hatcher property beginning at Station 24+30. The trench conditions were favorable with a dry base and stable sides. Occasional dewatering was necessary to remove groundwater. The trench excavation was through an area of hard shale, slowing progress but facilitating a good base for the pipeline. The pipeline was installed within the criteria in the plans and specifications. Two new manholes were installed at Station 27+10 and Station 29+50 in the approved manner. The 36- inch CCFRMP gravity sewer line was installed to Station 31+09 (MH-4) by the end of the week. GHBW performed compaction tests on the pipeline with all tests passing within the design specifications.

The utility crew worked on the SWPPP compliance issues. The seeding and mulching continued along the easement. The SWPPP report for this week detailed that the site stabilization for the easement was in compliance for the first time in several months. Max Hardin and members of the utility crew removed the water crossing at Station 102+00 and began the crossing at Station 139+00. Max Hardin stated that he had notified appropriate parties with ADEQ and The Ranch concerning his activities.
East End Conveyance -
Monday, November 16, 2009,
S.J. Louis crews continued with the installation of the ARV at Station 251+00. The crew placed the ARV and vent piping. S.J. Louis was requested to continue to the compaction efforts in County Farm Rd from Station 250+00 through Station 267+00.

Tuesday, November 17, 2009,
S.J. Louis utility crew worked on the maintenance of County Farm Road and Pinnacle Valley Road. The crew has the road in good condition. The area from approximately Station 250+50 to Station 253+00 needs continued compaction efforts to meet design limits for trench compaction. S.J. Louis will continue efforts in the area tomorrow. GHBW will be scheduled for testing when requested by the Contractor.

Wednesday, November 18, 2009,
S.J. Louis utility crew worked on the maintenance of County Farm Road and Pinnacle Valley Road. The crew has the road in good condition. The area from approximately Station 250+50 to Station 253+00 was the focus of the current maintenance efforts. GHBW is scheduled for testing from Station 250+50 to Station 267+00 tomorrow at 10:00 a.m.

Thursday, November 19, 2009,
S.J. Louis utility crew worked on the maintenance of County Farm Road and Pinnacle Valley Road. The S.J. Louis utility crew installed manhole extension rings for the ARV vaults located in County Farm Rd. and Pinnacle Valley Rd. GHBW was onsite for compaction testing from Station 250+50 to Station 267+00. All test were within design limits. Trench backfill compaction in County Farm Rd. and Pinnacle Valley Rd. is now complete, meeting or exceeding design specifications. Rick Roberts (Pulaski County) was onsite to identify areas in the opposing lane of County Farm Rd and Pinnacle Valley Rd damaged by construction traffic. These areas were marked for repair by the Contractor.

Friday, November 20, 2009,
S.J. Louis completed the installation of manhole ring extensions for the ARV vaults in County Farm Rd. and Pinnacle Valley Rd. S.J. Louis Crews also continued cleanup efforts along the 36-inch effluent pipeline easement and maintenance on SWPPP “best management practices”.

Saturday, November 21, 2009,
S.J. Louis utility crew continued pipeline easement cleanup and maintenance on County Farm Rd. and Pinnacle Valley Rd.