The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.
|
County Farm Rd. Waterline Relocation Project
|
|
Summary of Work Performed this week: 08/29/2009
|
|
Mike Hoggard, RPR, met with Billy Otts (CAW) and Brian Boroughs (S&J Construction) concerning the CAW water main relocation. Mr. Boroughs detailed his construction method and schedule for work. Mr. Otts was unsure if CAW had approved the project plans. He will make sure all is well with CAW, and contact the Contractor to proceed as planned. Mr. Boroughs will be staging pipe this week, and possibly begin laying pipe before the weekend. The staged 36-inch PVC pipe, Station 267+00 to Station 250+50, and one ARV vault must be relocated before S&J can proceed through this area.
|
|