EMERGENCY CONTACT: (501)223-1509


The Little Maumelle Treatment Facility and related construction projects are well underway. Read below to learn more.

Contract II: Construction of Wastewater Treatment Facility
Summary of Work Performed this week: 09/26/2009

Max Foote Construction Co. (MFCC) worked a five day work week.
Monday, 9-21-09, MFCC carpenters completed removing gang forms from the C-D pass wall. The labor crew began backfilling the U.V. channel floor base to the influent channel. The pipefitters began installing the 30 inch plant influent piping from the Entergy easement. The carpenters completed cleaning and removing formwork for the west Scum box. The carpenters continued installing decking for the Aeration Basin D-pass beams. The finishers continued to patch and repair the upper Aeration Basin walls. Notes: Site conditions are getting better.
Tuesday, 9-22-09, MFCC carpenters began installing the upper forms for the U.V. building influent box. The operators began excavating the east end of retaining wall-A. The pipefitters continued installing the 30-inch plant influent piping north of the U.V. building. The carpenters completed the sub-grade for the U.V. building influent channels. They have begun installing the perimeter forms for the channels. The carpenters resumed removing unused gang forms in the Aeration Basin. The finishers continued to patch and repair the upper Aeration Basin walls. The carpenters began installing gang forms for the south A-pass wall. Note: Site is very muddy and work activities were slow.
Wednesday, 9-23-09, MFCC carpenters continued installing the upper forms for the U.V. building influent box. The operators completed excavating the east end of retaining wall-A. The pipefitters continued fabricating the 30-inch pipe spools for the influent piping. The carpenters continued installing the perimeter forms for the U.V. channels. The finishers placed 75yds of concrete for the south Aeration A-pass wall. The finishers placed 14yds of concrete for the Influent mag-meter vault foundation. Note: Site is very muddy and work activities were slow.
Thursday, 9-24-09, MFCC fence contractor on the private road has completed post erection and have begun installing the horizontal railing. The operators built an access road on the west end of the retaining wall for the subcontractor. The pipefitters continued fabricating the 30-inch pipe spools for the influent piping. The carpenters continued installing the perimeter forms for the U.V. channels. The labor crew started cleaning and removing all materials from the Aeration Basin. The finishers continued to patch and repair the upper Aeration Basin walls. The carpenters worked installing gang forms for the north A-B pass walls. These walls are the tie-in to the RAS room walls for the Bypass system. The carpenters installed Weir gate block-outs for the Aeration outfall to the collection channel. Note: Site conditions have improved from the rain.
Friday, 9-25-09, MFCC fence contractor on the private road has completed the fence. The operators worked grading and cleaning the muddy areas of the plant. The pipefitters continued fabricating the 30-inch pipe spools for the influent piping. The carpenters continued installing perimeter forms for the U.V. channels. The labor crews continued cleaning and removing materials from the Aeration Basin. The carpenters worked installing the structural overhead door jams for the Odor Control building. The carpenters continued working installation of the Weir gate block-outs for the Aeration outfall to the collection channel. Note: Site conditions have improved from the rains.
Electrique Corporation: Subcontractor
E.C. worked installing under slab conduits for the U.V. building influent channels.
Jocon Incorporated Building Erectors: Subcontractor Jocon worked all week erecting the Filter building steel.
Midwest Coatings: Subcontractor
Midwest Coatings continued priming and painting the interior of the Odor Control building walls.
DMG Masonry: Subcontractor
DMG completed installing the brick veneer to the north face of the Odor Control building. They also continued installing CMU for the Headworks north and east walls.
Henley Construction: Subcontractor
Henley completed installing 17 course levels for wall-A and started installing wall-B behind the Admin building. The installation is complete with SB-2 backfill and all required density testing completed per specification.