County Farm Rd. Waterline Relocation Project
Summary of Work Performed this week: 09/26/2009

The CAW 12-inch waterline was crossed twice, with one more crossing required to complete the departure from Pinnacle Valley Road. S&J Construction installed approximately 950-feet of 8-inch DIP water line from Station 273+50 to Station 264+00. All pipes were installed according to design specifications. S&J will install hay bales for erosion control on Monday, September 28, 2009. S&J will install the fire hydrant at Station 264+25 on Monday, September 28, 2009.
Thursday, 9/24/09, Billy Otts, CAW, was onsite to inspect and observe the work. He was satisfied with the Contractor’s work and efforts to meet CAW specified standards